Message 1:

New Haven to Boston (AMtrak > Gov't contracting) electrified @ 2000 at $2.3 million/mile for mainly double track, some triple track. Populated almost all the way and very curvy (route along CN shore for much of way), both of which add costs ($200,000/mile for flagging !!)

I use $2 million/mile for single track and $2.5 million for double track with "round up" for large projects.

Combining electrification with HV transmission should reduce costs for both (certain % common towers).

Russia electrifies at $700,000 to $900,000/km (double track). Fewer people but extreme remoteness and extreme climate do add costs. No EIS required#

# Sierra Club is supportive of modified/simplified EIS for rail electrification, recognizing that rail ROW is already heavily impacted.

Message 2:

I stored this data (but forgot to mark where from, something I now do).

Russian Federal Railways) approximately $750,000 - 800,000 per kilometer to put a two-track line under AC wire (25kV, 50Hz).

the New Haven-Boston electrification cost about USD2.3m per route-mile (double track ie approximately USD0.7m per track-km) for "plain" track (no movable bridges, etc), broken down approximately as follows:

Design: $190,000
TPS--substations (@ $5/unit): $125,000
TPS--auto-transformers ($1.5/unit): $9,500
OCS @ $640,000/track mile: $1280,000
Signal Compatability/SCADA: $140,000
Flagging Protection: $200,000 [Outrageous]
Property Acquisitions: $30,000
Project Management: $90,000

Design/Build Cost Total: $2.3 million per route mile.

[OCS = "Overhead Contact System" = Catenary wires and supports.
"TPS" = "Traction Power System" = 4 25hv 60hz 80mvA substations and 21 autotransformers for a total of 360 track miles, 157 route-miles]
--------
Double track requires two OCS/track mile @ $640,000/mile. Single track one. The rest is about the same. Maybe less design and project management costs.

Again, gov't contracting costs. 
Comments:
Ok What is the point? What is the oil price at which the change over saves money?
 
The UK's East Coast Main Line electrification at the beginning of the 1990s cost £215,000 a single track kilometre (for a four tracked, very high traffic route with speeds of 125-140mph for top express trains and 90mph fast freight). Number includes civil works.

That's $555,000 a mile at today's exchange rate.

The ECML alignment is pretty straight and pretty flat (it's the old Great Northern Railway route), but that's hardly unknown in the US. More recent small projects have come in between £200,000-£260,000 on the same terms.
 
"What is the point? What is the oil price at which the change over saves money?"

That depends on the amount of traffic on a line and other factors (such as local property taxes on improvements).  Property taxes were a big factor in the decision of railroads to convert many double-track lines to single-track a couple decades ago.

Alan Drake has calculated that electrification of the lines which carry the bulk of ton-miles is profitable today.  Railroads may not have moved on this because they already have a large cost advantage in carriage of bulk cargo and availability of petroleum is not yet a factor; predatory local governments and property taxes are, sadly.

Thanks much for the figures, Alex.
 
Post a Comment



<< Home
Talk largely about energy and work, but also politics and other random thoughts


Mail Engineer-Poet

(If you're mailing a question, is it already in the FAQ?)

Important links

The FAQ
Glossary
The Reference Library

Blogchild of

Armed and Dangerous

Blogparent of

R-Squared




The best prospect for our energy future:
Flibe Energy

ARCHIVES
January 1990 / February 2004 / March 2004 / June 2004 / July 2004 / August 2004 / September 2004 / October 2004 / November 2004 / December 2004 / January 2005 / February 2005 / March 2005 / April 2005 / May 2005 / June 2005 / July 2005 / August 2005 / September 2005 / October 2005 / November 2005 / December 2005 / January 2006 / February 2006 / March 2006 / April 2006 / May 2006 / June 2006 / July 2006 / August 2006 / September 2006 / October 2006 / November 2006 / December 2006 / January 2007 / February 2007 / March 2007 / April 2007 / December 2007 / January 2008 / May 2008 / June 2008 / August 2008 / October 2008 / November 2008 / December 2008 / February 2009 / March 2009 / April 2009 / May 2009 / June 2009 / July 2009 / August 2009 / September 2009 / October 2009 / November 2009 / December 2009 / January 2010 / April 2010 / May 2010 / June 2010 / July 2010 / August 2010 / September 2010 / October 2010 / November 2010 / December 2010 / January 2011 / February 2011 / March 2011 / April 2011 / May 2011 / July 2011 / August 2011 / September 2011 / October 2011 / April 2013 / November 2013 / December 2013 / January 2014 / February 2014 / March 2014 / April 2014 / July 2014 / August 2014 / September 2014 / October 2014 / November 2014 / February 2015 / April 2015 / October 2015 / March 2016 / April 2016 / May 2016 / June 2016 / July 2016 / November 2016 / December 2016 / February 2017 / May 2017 / June 2017 / September 2017 / October 2017 / November 2017 / March 2018 / May 2018 / June 2018 / October 2018 / December 2018 / January 2019 / March 2019 / June 2019 / October 2019 / November 2019 / March 2020 / June 2020 / December 2020 / March 2021 / April 2021 / May 2021 / July 2021 / January 2022 / February 2022 /


Powered by Blogger

RSS feed

Visits since 2006/05/11: